Case Studies THERMAL-XR® Projects

THERMAL-XR® CASE STUDY | Indonesian Data Center, ~7.2% Energy Reduction

Baseline current and temperature data were collected prior to the installation date of THERMAL-XR®. The test of the energy savings performance of THERMAL-XR® system, a total of 5 PAC’s serving one floor of the data center. Stable indoor loads (not set point change, consistent student-athlete presence) PDF version Indonesian Data Center For more THERMAL-XR® Projects […]

Case Studies THERMAL-XR® Projects

THERMAL-XR® CASE STUDY | Texas USA, High School, Gymnasium, ~36.7% Energy Reduction

Baseline current and temperature data were collected prior to the installation date of THERMAL-XR®. Continuous amp monitoring using Monnit 3 Phase Current Monitor  Automatic cloud capture of current data every 30 minutes.Stable indoor loads (not set point change, consistent student-athlete presence)   PDF version Texas High School Gymnasium August 2023 For more THERMAL-XR® Projects | […]

Press Release TXR News, Installed & Tested

GMG APPOINTS NU-CALGON AS THERMAL-XR® DISTRIBUTOR FOR NORTH AMERICA

Graphene Manufacturing Group Ltd. (TSX-V:GMG) (“GMG” or the “Company”) is pleased to announce that GMG has signed a THERMAL-XR® distribution agreement with Nu-Calgon Wholesaler, Inc (“Nu-Calgon”). Nu-Calgon is the leading Heating Ventilation Air Conditioning, and Refrigeration (HVAC-R) specialty chemical supplier in North America and will partner with GMG to provide THERMAL-XR® to the HVAC-R markets […]

Case Studies THERMAL-XR® Projects

THERMAL-XR® CASE STUDY | SINGAPORE AVIATION IT CENTRE, ~15.4% IMPROVEMENT

HERMAL-XR® CASE STUDY | SINGAPORE AVIATION IT CENTRE, ~15.4.% IMPROVEMENT • Regression Analysis + Pre & Post Energy savings calculation/estimates. • Consistent climatic and operational conditions. More Information click Singapore Aviation IT Centre March 2023 For more THERMAL-XR®Projects | www.graphenemg.com/thermal-xr-projects/ Contact GMG for further information and/or partnership enquiries and installations [email protected] www.graphenemg.com  |  TSXV: GMG DISCLAIMER […]

Case Studies THERMAL-XR® Projects

THERMAL-XR® CASE STUDY | SINGAPORE HOSPITAL, ~24.3% IMPROVEMENT

THERMAL-XR® CASE STUDY | SINGAPORE HOSPITAL, ~24.3% IMPROVEMENT • Customer energy savings calculation estimates. • Consistent climatic and operational conditions. • Vital air-conditioning system for the operations theatre, running 24 hours, 7 days a week. The customer’s feedback was, “Our capex is extended, and equipment life increased by an estimated 5 to 7 years and saved […]

THERMAL-XR® Projects

THERMAL-XR® PROJECT UPDATE: 8% Energy Reduction Cold Room Storage Facility Singapore

THERMAL-XR® PROJECT UPDATE: Cold Storage Facility in Singapore Savings, 8% Energy Reduction After coating with THERMAL-XR® on a Singapore, Residential air conditioner, a 8% Energy Reduction was measured by management regression analysis estimate. Energy Reduction 8% Measurement Days 76 days Unit Refrigerated System Date March 2021 Calculation Method GMG Management Estimate Calculation Pre vs Post […]

THERMAL-XR® Projects

THERMAL-XR® PROJECT UPDATE: HEALTH & FITNESS CLUB # 3, 22% ENERGY REDUCTION

THERMAL-XR® PROJECT UPDATE: HEALTH & FITNESS CLUB #3, 22% ENERGY REDUCTION  After coating with THERMAL-XR® on a Brisbane Health & Fitness Club 85 kW Air Conditioner, a 22% Energy Reduction was measured by management regression analysis estimate. Energy Reduction 22 % Energy Savings 1482 kWhr | Annualised Estimate 27046 kWhr Emission Savings 1187 CO2 kg […]

THERMAL-XR® Projects

THERMAL-XR® PROJECT UPDATE: 6.5% Energy Reduction Poultry Processing Facility Singapore

THERMAL-XR® PROJECT UPDATE: Poultry Processing Facility in Singapore Savings, 6.5% Energy Reduction After coating with THERMAL-XR® on a Poultry Processing Facility in Singapore, a 6.5% Energy Reduction was measured by management regression analysis estimate. Energy Reduction 6.5% Energy Savings 747 kWhr | Annualised Estimate 18177 kWhr  Emission Savings 149.3 CO2 kg | Annualised Estimate 3625 […]